From The Manager
Mel Nunn
I met with Janet Wojciechowski and Gary Bell on Wednesday, March 29, 2000, to schedule maintenance of the units north of Island Drive. The contractor needs three days for each phase III unit and four days for the other units. These repairs include the following:
It is our intent to have the area North of Island completed by the May 18, 2000. This includes all trees trimmed to approximately 10 feet in height, have the golf course area visible to the units, have the fence completely repaired, the trash can enclosures repaired, the lawn cleared of pine cones and needles, irrigation system adjusted and some ladder fuels reduction completed between our entrance and Abbott.
The Unit maintenance schedule is as follows:
| Dates | Units |
|---|---|
| Apr 3 - 5 | 53 and 54 |
| Apr 6 - 8 | 61 and 62 |
| Apr 10 - 12 | 59 and 60 |
| Apr 13 - 15 | 57 and 58 |
| Apr 17 - 19 | 55 and 56 |
| Apr 20 - 22 | 65 and 66 |
| Apr 24 - 26 | 63 and 64 |
| May 1 - 4 | 47 and 48 |
| May 8 - 11 | 51 and 52 |
| May 15 - 18 | 49 and 50 |
I appreciate the cooperation of Janet and Gary of the Lodge. This schedule also will be coordinated with the other rental agents. We will start coordinating the schedule for all units South of Island with the realty agents around mid April. We hope to complete all the units no later the end of July, with the caveat that weather plays an important factor in this ambitious schedule. I think that around mid May the Wildflower II Owners, Sunriver lodge guests, realtors, golfers, employees and contractors will recognize the improvements in our Community.